Construction supervision activity related to the installation of the overhead line and power supply system in the Mezőzombor – Sátoraljaújhely railway line section.
Project objective:
Area lighting was moderinsed in all railway stations and stops with the installation of state-of-the-art acoustic and visual passenger information equipment in order to increase passenger comfort. 55 cm high platforms were built at the stations with the necessary transformations of the track network. To ensure safe transport in winter, electric point heating equipment was installed in the stations and a train pre-heating unit was established in Sátoraljaújhely. New, overridden D-55 interlocking equipment equipped with axial counter was installed in the stations and a modern Centralised Traffic Control operator centre was established in Sátoraljaújhely.
In the Sárospatak – Sátoraljaújhely station interval, the earthwork which also has flood protection function was raised by 1 m in 4 km lenght, decreasing the risk of rail traffic interruption due to flooding by the Bodrog River.
The construction investment involved the refurbishment of more than 11 km railway track.
Project completed: 2 July 2019
Investment value: HUF 23,033,223,757
During the project, our Company has been assigned with project management, execution direction tasks and provided the majority of construction supervisors in the specialised fields. Our activities also included cost control and quantity surveying tasks, as well as certification of the Contractor’s monthly and overall performance.